Development Phasing
Four Phases. One Gigawatt-Scale District.
The initial development plan contemplates four major phases, each anchored by approximately 250MW of data center capacity and a coordinated mixed-use program.
The schedule below is preliminary and intended to guide partner, tenant, investor, and municipal engagement. Dates are planning targets, not contractual commitments.
Now Forming
250 MW
250 MW total
Q4 2029
Phase 2
+ 250 MW
500 MW total
Q4 2030
Phase 3
+ 250 MW
750 MW total
Q2 2032
Phase 4
+ 250 MW
1 GW total
Q4 2033
Phase 1
Now FormingDistrict Launch Phase
The first tower. The first street. The first community.
Capacity
250 MW
250 MW cumulative
Target Opening
Q4 2029
Tenant Occupancy
Q3 2029
Phase Program
- 250MW data center capacity
- First mixed-use tower / podium
- One or two major anchor tenants
- Initial retail and restaurant street
- Premium office component
- First residential tower or residential-over-podium
- District operations center
- First district thermal loop segment
- High-speed connectivity and managed tenant services
- Structured parking / mobility hub / EV charging
Phase 2
Expansion District
Scaling the district — more capacity, more community.
Capacity
+ 250 MW
500 MW cumulative
Target Opening
Q4 2030
Tenant Occupancy
Q3 2030
Phase Program
- Additional 250MW data center capacity
- Second tower / district block
- Expanded retail, office, and entertainment uses
- Additional residential or hospitality component
- Expanded thermal reuse network
- Additional public realm / plaza / events space
Phase 3
Destination District
A district that draws people — not just tenants.
Capacity
+ 250 MW
750 MW cumulative
Target Opening
Q2 2032
Tenant Occupancy
Q1 2032
Phase Program
- Additional 250MW data center capacity
- Third tower / district block
- Larger hospitality, conference, wellness, or entertainment anchor
- Expanded managed services and district mobility systems
- Deeper heat-reuse offtake opportunities
- Mature commercial tenant ecosystem
Phase 4
Full Giga Zone Buildout
One gigawatt. One complete district.
Capacity
+ 250 MW
1 GW cumulative
Target Opening
Q4 2033
Tenant Occupancy
Q3 2033
Phase Program
- Final 250MW data center capacity
- Fourth tower / district block
- Total planned 1GW district compute capacity
- Full mixed-use district program
- Complete district utility, connectivity, operations, mobility, and services platform
Schedule Note: Dates are planning targets for tenant, partner, and investor engagement. Final delivery dates will depend on site selection, entitlement path, utility studies, financing, development agreements, construction sequencing, and tenant requirements.
Engage with Phase 1 formation now.
Phase 1 represents the first opportunity to shape the district program. Anchor tenant, investor, and site-owner conversations are being organized now ahead of site selection.